53 MULTI-OCCUPANCY ACCOMMODATIONS

The project Construction of 53 blocks of flats, broken down as follows:– One building with 11 flats, comprising a ground floor and three storeys– One building with 9 semi-detached flats, comprising a ground floor and two storeys– One building with 33 flats, comprising a ground floor and four storeys Project owner ARKADEA 41 rue Camille […]

Housing
Roads and Utility Networks Structure Thermal studies Fluids and utilities Electrical Engineering

The project

Construction of 53 blocks of flats, broken down as follows:
– One building with 11 flats, comprising a ground floor and three storeys
– One building with 9 semi-detached flats, comprising a ground floor and two storeys
– One building with 33 flats, comprising a ground floor and four storeys

ARKADEA

41 rue Camille Desmoulins

92130 ISSY-LES-MOULINEAUX

T. 03 20 88 50 00

ICADE

POSTE IMMO

Planning phase: 2020 – ACT phase currently underway

Expected start date for the works: first quarter of 2022

(Duration: 21 months)

4 556 100 € H.T.

OYAPOCK architectes

– RT2012
– Label E2C1
– NF HABITAT

3092m² SHAB